Migration Plan and Next Steps

Migration Plan

Migration of all Sitecore websites must be completed before the existing Sitecore license expires in December 2020. To meet that deadline the following actions will be taken.

  • Site migration will be like for like. This means that the existing site structure, design and content in Sitecore will be moved to Cascade without changes when the site migrates.
  • Site owners should make every effort to review their existing sites to remove unnecessary content prior to migration.
  • University Relations will manage the migration with the aim to automate the process as much as possible.
  • Site owners will be responsible for validating content and making manual adjustments after the migration.
  • Site migration will be phased starting with the institutional pages to refine the migration process.
  • University Relations will begin meeting with site admins in summer of 2019 to determine migration schedules.

Next Steps

Training

  • UR staff technical training (completed – early April 2019)
  • UR Migration training (May 1, 2019)

Infrastructure Set-up

  • Installation and configuration of CMS on the university’s cloud servers (target – May 2019)
  • Institutional framework (HTML/CSS) updated for Cascade CMS (target – summer 2019)

Migration Schedule

  • Content migration schedule built for all affected sites (target – fall 2019)